1+
# Release Process and Timeline
2+
3+
## Instance Updates with New Releases
4+
5+
All future updates will follow a standardized release process:
6+
7+
- Updates will be scheduled over the **weekend** to minimize disruption.
8+
- Users will receive an **email notification by the preceding Wednesday**, informing them that Specify may be inaccessible for up to **12 hours** during the weekend.
9+
- **Jason** will confirm the exact 12-hour downtime window with **Grant**, who will then relay the information to users.
10+
- Once the update is complete, users will receive a **follow-up email** confirming that the update was successful.
11+
12+
---
13+
14+
## Timeline: Testing + Update
15+
16+
### Week 1
17+
- **Monday–Friday**: General testing begins and is completed by **Friday**.
18+
- **Friday**: KU test instances are updated to the latest version.
19+
- **Friday Night**: Open testing week begins (email notification is sent).
20+
21+
### Week 2
22+
- **Wednesday**: Release announcement email is sent to users, including downtime window.
23+
- **Friday Night**: Open testing week ends.
24+
- **Saturday or Sunday**: Production update is performed during the confirmed 12-hour window.
25+
> During this time, **Specify will be inaccessible for up to 12 hours**.
26+
> All hosted instances will be updated simultaneously. Institutions that do not wish to be updated must wait for the next release cycle.
27+
- **Monday**: Follow-up email is sent confirming that the update was successful.
28+
29+
---
30+
31+
## Summary Timeline
32+
33+
| Week | Day | Activity |
34+
|------|------------------|--------------------------------------------------------------------------|
35+
| 1 | Monday | General testing starts |
36+
| 1 | Friday | General testing completed |
37+
| 1 | Friday | KU test instances updated to latest version |
38+
| 1 | Friday Night | Open testing week begins (email sent) |
39+
| 2 | Wednesday | Release announcement + downtime email sent to users |
40+
| 2 | Friday Night | Open testing week ends |
41+
| 2 | Saturday/Sunday | Production update (Specify inaccessible for up to 12 hours) |
42+
| 2 | Monday | Follow-up email confirming successful update |

0 commit comments