Resource libraries
If you work on several projects with the same crews, the same subcontractors and the same calendars, you don't want to maintain their rate, calendar and type separately in every project — retyping them each time and chasing every copy when something changes. That's what a resource library is for: a shared source of resources and calendars that belongs to your organization, lives outside individual projects, and multiple projects can draw from. This guide explains how the library relates to a project, exactly what travels along and what stays per project, and how you switch between the two.
- The distinction between the library (shared, organization-wide) and the project (what this project actually uses).
- Linking a project to a library, or deliberately leaving it standalone.
- The two views on the Resources tab: Library and Project.
- The three kinds of rows you'll meet in the project view: from the library, project-only, and orphaned.
- Exactly what a library resource brings into the project, and what you set freely per project.
- The three actions that connect the library and the project.
- How the app refreshes copies, and what you get to decide when a copy has drifted.
- Sharing, backup, and their limits.
Follow along with Nieuwbouw 6 Rijwoningen De Akkers and Nieuwbouw Appartementencomplex De Vaart: opening either showcase automatically links it to one shared demo resource library, and the crews Timmerlieden, Installateurs, Stukadoors and Schilders reappear under the exact same name in both — direct proof that one library feeds multiple projects.
The resource library is the shared source: it belongs to your organization, not to a single project, and outlives any individual project. The project decides what this specific project actually puts to work from it — with its own capacity, availability and calendar choice. A project links to exactly one library, or stands entirely on its own: in that case everything simply works as usual, just without a shared source to draw from or write back to.
You choose the library in two places, which show the same panel:
- The new project wizard ("New project"), with a library selector.
- Project info for an existing project — both the dialog and File → Project info.
That same selector also has + New resource library…, letting you create one on the spot without first going to File → Library. None (standalone project) is an explicit choice in the same list — unlinking your project is never an accidental side effect, it's always something you choose deliberately.
Once a project is linked to a library, the Resources tab gains a toggle in the top right with two views:
- Library — manage the source itself. Everything here is directly editable, a change applies immediately to every project drawing from this library, and it falls outside undo (Ctrl+Z) — it isn't a project edit.
- Project — what this project actually uses: the regular project table, with per-row markers for provenance and any deviations.
In the project view you'll encounter three kinds of rows:
- From the library — marked with the From the library badge. Name, type, rate/hour and unit are inherited from the library and shown here as plain text: you don't edit them here, but in the Library view. Max units, the time-phased availability and the calendar choice are freely editable, though — that's exactly this project's own commitment.
- Project-only — no badge, fully editable. Even a linked project can have these rows: useful for one-off items that don't belong in the shared library, such as a rented crane or a subcontractor hired for this single job.
- Orphaned — the library original is gone; the row is marked no longer in the library. The copy itself keeps working fine — you can unlink it or delete it.
This is the part worth remembering: some fields are a company-wide agreement and follow the library, others are this project's own commitment and you set them freely, without that ever counting as a deviation.
Follows the library:
- Name
- Type
- Description
- Rate/hour
- Unit
- The content of a calendar that travelled along with a resource (work days, hours, holidays)
You decide per project, without it counting as a deviation:
- Max units
- The time-phased availability
- The choice of which calendar is attached to the resource
Assign a library resource, and its calendar travels along as a linked copy that itself keeps following the library — which is why the content of that calendar sits in the left-hand list above. But the choice of which calendar is attached to a resource sits in the right-hand list: the same crew might run on a different calendar for a rush job than it normally would, without that being a deviation from the library. This distinction is subtle but important: change a library resource's rate or name, and the copy deviates from the library; change its calendar choice or max units, and you're doing exactly what that field is there for.
- Assign to project — from library to project: creates an editable copy with provenance.
- To the library — from a project-only row into the shared library: links it immediately. If an item with the same name already exists in the library, the app links to that one instead of duplicating it.
- Unlink from library — provenance disappears, everything becomes fully editable again. A calendar that travelled along unlinks with it, unless another still-linked resource is using that same calendar.
The app checks whether your copies still match the library at four fixed moments: when opening a file, when switching documents, after an edit in the library, and after crash recovery.
- If a copy has simply fallen behind (you haven't changed it yourself, but the library has moved on since), it's refreshed silently — you'll just see a brief notice, no question.
- If a copy has been changed locally (or by someone else), the differs — decide marker appears, and the app asks per item what should happen: Use library values, Adopt file values into the library, or Decide later.
These choices can't be undone with Ctrl+Z — the second option changes the library itself, which sits outside the project's undo history altogether.
A project file is always self-contained: hand it to someone without your library, and everything still works, just without a shared source. You export and import a library via File → Library — that's also your backup.
When you import, you choose between two options:
- Add as new resource library — the library from the file is simply added, as an extra library alongside your existing ones, and never overwrites anything of yours. If the sender had already split off a second library of their own (say, for a separate subcontractor), that library carries its own identity along with it: a project sent together with it immediately recognizes the crews and calendars it was already using as library items again, with nothing for you to sort out. If the sender only ever had one library that was never split off — the everyday case for most people — that automatic recognition doesn't kick in: you link the sent project to the new library yourself, just once, after which matching by name takes over. If you already have that exact library, it's added as a separate copy alongside it instead.
- Replace an existing resource library — the entire contents of the library you pick are overwritten with what's in the file. If your own version is newer than the one you're importing, the app warns you about that beforehand.
Which option is preselected depends on the file: if the app doesn't recognize the library yet, "Add as new resource library" is selected; if it does recognize it (the same library, a different version), "Replace an existing resource library" is selected with that library already chosen.
Libraries don't synchronize between machines on their own: if two planners work with the same library on different computers, the libraries can drift apart.
Open one of the showcase examples (File → Examples, or from this Help panel), and the app creates a Demo-resourcebibliotheek once and links the opened example to it. Nieuwbouw 6 Rijwoningen De Akkers and Nieuwbouw Appartementencomplex De Vaart share the same crews from that library, so you can immediately see how one library feeds multiple projects. Your own existing resource libraries are left completely untouched.
- Assigning resources, reading the histogram, and leveling are all about the project side of resources — read the guide Resources, histogram & leveling.
- A resource's linked calendar uses the same building blocks as any other calendar — read the guide Calendars & hour planning.
- See crews shared between projects for yourself in Nieuwbouw 6 Rijwoningen De Akkers and Nieuwbouw Appartementencomplex De Vaart.
public/docs/en/ and docs/wiki/ — direct wiki edits are overwritten on the next release.
Open Planner Studio · LGPL-3.0 · part of the OpenAEC-Foundation
Open Planner Studio
Getting started
Guides
- Planning & WBS
- Relations & constraints
- Calendars & hour planning
- Resources, histogram & leveling
- Resource libraries
- Baselines & progress
- Critical path & advanced analysis
- Import/export
- Connecting an AI assistant (MCP)
- Reports & printing
- Keyboard shortcuts & controls
Reference
- Task dialog
- Calendar dialog
- Resource calendar
- Leveling options
- Baseline management
- External links
- Codes & fields (structure)
- Filters
- Choosing columns
- Saving and loading layouts
- Project information
- Settings
- Managing and installing extensions
- Recovering after a crash
- Keyboard shortcut reference
Project